Custom Pajama Bulk Production Process

1. Sample Confirmation: Ensure both fabric and workmanship are approved.
2. Production Kick-off: Start bulk production after receiving a 30% deposit and confirming the pre-production sample.
3. Fabric Preparation: Produce fabrics (20 -30 days).
4. Garment Sewing: Sew the garments (10 -15 days).
5. Inspection: Conduct quality checks (1 -3 days).
6. Packing List Submission: Provide the packing list.
7. Shipping Cost Inquiry: Obtain shipping cost quotes based on the packing list weight.
8. Shipping Options Proposal: Send customers various shipping method quotations and assist in choosing the best option.
9. Shipping Arrangement: Arrange shipment upon confirmation of the shipping method and receipt of the shipping cost.
10. Transit Times: Sea shipping takes about 30 days; air shipping takes 9 - 12 days.
11. Direct Delivery: Ship directly to the customer's warehouse (customers don't need to handle customs clearance or pay taxes).